MLAGs between fully managed switches

A multi-chassis link aggregation (MLAG) allows multiple switches to collaborate as a unified logical switch. An MLAG allows links that are physically connected to two different devices to appear as a single port channel to another device.

The port channel partner device is not aware that it is connected over a port channel to two peer switches. Instead, the two switches appear as a single switch to the partner with a single MAC address. All links can carry traffic across a physically diverse topology and in the case of a link or switch failure, traffic can continue to flow with minimal disruption.

M4500 series MLAG

You can use the controller to create and configure the following two types of MLAG on an M4500 series switch:

For an M4500 series switch to form an MLAG with a partner switch, the following are required:

  • Onboard two or four M4500 series switches of the same model to the controller.
  • Enable Auto-LAG and Auto-Trunk on all M4500 series switches you intend to use in an MLAG.
  • Ensure all ports on the M4500 series switches are unconfigured before you create an MLAG.
  • Define and connect the MLAG ports on the M4500 series switches.
Note: The M4500 series switches do not perform DHCP. Another switch in your network must serve as a DHCP server and assign IP addresses to your network devices, including the M4500 series switches.
Note: For MLAG peer switches that were configured outside the controller, only the single-tier MLAG option is supported.

M4350 series MLAG

The controller does not support MLAG creation or management for M4350 series switches. You must create a single-tier MLAG on M4350 series switches using the device CLI or the device UI before onboarding the switches into the controller.

Note: Double-tier MLAG is not yet supported on M4350 series switches.

Once an M4350 single-tier MLAG pair is onboarded, you can view MLAG status and information in the controller but cannot create or modify the MLAG configuration. For more information, see View M4350 MLAG information in Engage.

For an M4350 series switch to form an MLAG with a partner switch, the following are required:

  • Configure a single-tier MLAG on both M4350 series switches using the device CLI or device UI. For more information, see netgear.com/support/enterprise/.
  • Allow at least one polling cycle (approximately 40 seconds) after onboarding for the controller to detect MLAG status on both switches.