Create a stack of two fully managed switches

From the controller, you can set up and manage a stack of two fully managed switches, for example, to create a redundant core. After you configure two stacked switches, the controller displays the stacked switches as a single logical unit.

Note: The controller supports stacking for M4300 series switches and M4350 series switches only.
Note: Stacking and PTP residency time stamping (also referred to as PTPv2 transparent clock) are mutually incompatible. For a stack to be formed, you first might need to use the device UI of a participating fully managed switch to disable PTP residency time stamping for any network profiles that use it.

To create a stack of two fully managed switches:

  1. On your computer, in the folder in which you installed the controller application, double-click the Engage application icon, or double-click the Engage shortcut.

    The controller application opens and displays a login page.

  2. In the Login Name field, enter admin as the user name, in the Password field, enter the controller password that you set up the first time that you logged in, and click the Login button.

    The Managed Devices page displays.

  3. If you set up more than one site, from the Site menu, select the site.

    The Edit Network Setup pop-up window displays.

    Do one of the following:

    • Make no changes to the network setup for the site: Click the Apply button.
    • Change the network setup for the site: See the information in Edit the network setup of a site. When you are done, click the Apply button.

    The Managed Devices page adjusts.

  4. Select the check box to display Physical Devices and/or Virtual Devices.
    By default, all managed devices display. Use the Device Model menu to select individual devices.
  5. In the table, for a stackable switch, click the 3 dots icon and select Stack.

    The Create Stack pop-up window display.

  6. From the Select Stack menu, select the partner switch for the stack.

    Only switches that are stackable display.

  7. Click the Next button.

    The window adjusts.

  8. In the Device Name field, enter a name for the stack.

    The name is for identification purposes only.

  9. Set one of the switches as the stack management switch by enabling the Management toggle in the graphic display for the switch so that the toggle displays blue or green and is positioned to the right.

    The Management toggle for the other switch is disabled, displays gray, and is positioned to the left. The other switch functions as the standby switch in the stack.

  10. In the graphical display for each switch, select the stack port or ports.

    The stack ports form the stack connection between both switches. You can assign up to eight stack ports to establish the connection between the management switch and the standby switch.

  11. Click the Next button.

    The window adjusts.

  12. Click the Create button.

    The Validate Port Connection pop-up window displays.

  13. Click the Yes button.

    The port connections are verified. If the process is successful, the window adjusts and displays a confirmation message.

  14. Click the Reboot Now button.

    The two switches in the stack reboot. After the switches complete the reboot process, the controller displays the stacked switches as a single logical unit.

    In the Managed Devices table, a green X icon displays in the upper right corner of the switch product image to indicate the stack. To see the details of the switches included in the stack, point to the icon.